Adding a Second Vertical Axis to a Simulation Graph
By default, in a simulation graph, a single vertical axis appears on the left side of a curve. You can add a second vertical axis to the right of a curve.
To add a vertical axis:
Select a plot.
Select a variable from the Variables palette of the Simulation Results tab.
Right-click on the variable and select Add to Secondary Plot Axis. A new axis is added to the graph.
Note: You cannot add a variable to the second vertical axis if it is already plotted on the primary axis. If you try to plot the same variable on both primary and secondary axes, the Move Plot Variable dialog opens and asks if you want to move the variable to the secondary axis. Click OK to move the variable to the secondary axis.
See Also
Adding a Variable to a Graph
Using Variables Palette in the Simulation Results Tab